Quiz 06
When planning a project, one should take into account:
a. Any special training
b. The overall objectives of the firm
c. Any anticipated difficulties
d. All the above
e. None of the above.
The PM should get concurrence on the elemental task descriptions from:
a. Those who will be doing the work
b. The supervisor of those doing the work
c. Top management
d. All the above
e. None of the above.
According to the authors, any project plan must contain all of the following except :
a. Evaluation methods
b. Contractual aspects
c. Resouces
d. Potential problems
Which of the following is a guideline in achieving the objectives of systems
integration?
a. design components to optimize the performance of each subsystem
b. make component requirements traceable to one or more system requirements
c. require strict component performance specifications
d. never underdesign the performance characteristics specified by the client
e. none of the above
Which of the following is used to highlight critical interfaces between units?
a. the project action plan
b. the work breakdown structure
c. the linear responsibility chart
d. the project master schedule
e. the network diagram